KEFI Resumes Development at Tulu Kapi Gold Project in Ethiopia

StockMarket.et · 3 hours ago · Read the Full Story on StockMarket.et
KEFI Resumes Development at Tulu Kapi Gold Project in Ethiopia
AI SUMMARY

KEFI Gold and Copper has resumed development at Ethiopia's Tulu Kapi Gold Project following a temporary suspension due to a fatal security incident in September 2026.

  • KEFI Gold and Copper resumed development at the Tulu Kapi Gold Project in Ethiopia following a temporary suspension.
  • The suspension was triggered by a fatal incident on September 4, 2026, referred to as the Genji Incident.
  • The incident was resolved on September 10 after engagement with local community leaders.
  • The event marked the first fatality involving KEFI personnel during the company's 12 years in the project.
  • During the suspension, senior management consulted with community representatives, government officials, security agencies, and stakeholders.
  • The restart will begin with reconnecting the site to the regional electricity grid and remobilizing civil engineering teams for access roads.
  • Subsequent phases will involve resettlement arrangements, security infrastructure upgrades, and earthworks for the processing plant.
  • The project is expected to directly employ approximately 1,000 local people once active production is reached.
  • International specialists and contractors will prioritize local businesses with operational experience in Oromia.
  • The resumption follows a mining services agreement signed with BCM Group in June 2026 valued at over $400 million.
  • International lenders remain committed to the project as discussions continue regarding timelines and financing arrangements.