Parallel efforts underway to restore Addis West power substation

TIKVAH Ethiopia · 3 hours ago · Read the Full Story on TIKVAH Ethiopia
Parallel efforts underway to restore Addis West power substation
AI SUMMARY

Ethiopian Electric Power is pursuing two parallel solutions, including transporting a replacement transformer from Arba Minch and repairing the damaged unit in Addis Ababa, to restore service at the malfunctioning Addis West substation.

  • Ethiopian Electric Power is implementing two parallel solutions to restore service at the Addis West power substation following a technical failure.
  • Transporting a replacement transformer from Arba Minch began two days ago using a low-bed trailer and three Isuzu vehicles.
  • The convoy carrying the replacement transformer is traveling at an average of 50 to 70 kilometers per day with survey experts clearing the route ahead.
  • Simultaneously, the damaged transformer is undergoing repairs at the Gelan Workshop Center in Addis Ababa.
  • Whichever option between the repairs and the transported replacement transformer finishes first will be utilized to provide urgent power.
  • The replacement transformer from Arba Minch may require minor civil engineering work due to technical specification differences.
  • An exact completion date cannot be set due to the complexity of the technical work and transport conditions.
  • Ethiopian Electric Utility stated that service will be fully restored once the transformer arrives and technical issues are resolved, asking customers for patience.
  • Residents in several areas of Addis Ababa have been experiencing power outages for the past 15 days.