ERC Aims to Complete Awash–Kombolcha Railway in Two Years
Capital Ethiopia · 2 hours ago · Read the Full Story on Capital Ethiopia

AI SUMMARY
The Ethiopian Railway Corporation plans to finish the Awash–Kombolcha–Woldiya–Hara Gebeya railway project within two years following the resolution of a compensation dispute with Yapı Merkezi.
- The Ethiopian Railway Corporation plans to complete the remaining construction of the Awash–Kombolcha–Woldiya–Hara Gebeya railway project within two years.
- The 392-kilometer railway project was initially awarded to Turkish contractor Yapı Merkezi in August 2015 under a $1.7 billion contract.
- A four-year arbitration dispute in London concluded on September 23, 2026, resolving the contract performance, delay, payment, and war damage disputes.
- The arbitration ruling ordered Ethiopia to pay Yapı Merkezi $213.7 million in damages including nine percent interest, alongside $29.1 million in advance payments.
- The damages include $67.4 million in unpaid amounts, $76.7 million for construction delays, and $89.2 million for asset damage during the northern conflict.
- Yapı Merkezi had initially sought over $1 billion in compensation, while Ethiopia filed a $400 million counterclaim.
- A 27-member Ethiopian team of experts, led by Addis Ababa University law professor Tilahun Teshome, represented the country in the arbitration.
- The tribunal dismissed claims against the Ministry of Finance and the Ministry of Transport and Logistics, reducing the risk of overseas asset enforcement.
- The tribunal ordered Yapı Merkezi to transfer project vehicles and machinery to the ERC.
- Yapı Merkezi announced it was awarded $307 million, with the ERC attributing the discrepancy to differences in interest calculation periods.
- Neither the ERC nor Yapı Merkezi currently intends to appeal the decision within the 28-day window.
- The ERC is also focused on repairing railway infrastructure damaged by conflict and earthquakes, with work underway in Kombolcha and Dessie.
Related
30 Percent of Ethiopia's Population Isolated Due to Lack of Roads, Report Says
The Reporter (Amharic) · 5 hours ago
New System Launched to Measure Ethiopia-Djibouti Trade Corridor Logistics Performance
The Reporter (Amharic) · 5 hours ago
Ethiopian Railways Ordered to Pay Turkish Contractor $307.6 Million
Addis Standard · 3 days ago
Ethiopian Electric Utility Restores Power After Addis West Substation Repair
TIKVAH Ethiopia · 3 days ago