Government Steps In to Finish Kombolcha Railway as London Arbitration Nears Conclusion

The Reporter · 5 hours ago · Read the Full Story on The Reporter
Government Steps In to Finish Kombolcha Railway as London Arbitration Nears Conclusion
AI SUMMARY

The Ethiopian government has taken over the restoration of the stalled Awash-Kombolcha-Hara Gebeya railway line using internal resources while legal arbitration with the former contractor nears its end.

  • The Ethiopian Railways Corporation has taken over the restoration of the Awash–Kombolcha–Hara Gebeya railway line using its own workforce, machinery, and materials.
  • State engineers have successfully defended against more than 70 percent of the claims brought by former contractor Yapı Merkezi.
  • Remaining disputes regarding outstanding payments and machinery continue at the London Court of International Arbitration following an initial one-billion-dollar war damage claim by Yapı Merkezi.
  • State workers have repaired approximately 70 kilometers of track and plan to initiate test runs soon.
  • Phase One up to Kombolcha is targeted for completion within two years.
  • The 392-kilometer project began construction in 2015 under a USD 1.7 billion contract backed by European and Turkish financial institutions, featuring 12 tunnels and 52 bridges.
  • A full assessment of total restoration costs remains pending due to ongoing legal arbitration.
  • A localization study presented at the 27th EACE Convention estimated that domestic firms can deliver 68.3 percent of the value across four major railway contracts worth USD 6.53 billion.
  • Local companies are equipped for foundational tasks like earthworks and station construction, while complex systems such as signaling and electrification still require imported technology.