Allied Gold has connected the Kurmuk Gold Mine in western Ethiopia to the national grid and entered the final stages of commissioning ahead of its first gold pour.
- Allied Gold Corporation connected the Kurmuk Gold Mine in Benishangul-Gumuz to Ethiopia’s national electricity grid on September 17.
- The 88-kilometre, 132-kV transmission line and associated substations were completed by Ethiopian Electric Power.
- Electricity is supplied under a 20-year power purchase agreement at a fixed rate of approximately US$0.04 per kilowatt-hour.
- The mine has fed its first ore through the crushing circuit and is preparing to introduce ore into the grinding and downstream processing circuits.
- Mining operations at the Dish Mountain and Ashashire open pits have stockpiled roughly one million tonnes of ore, with a target of 1.5 million tonnes before full-circuit commissioning.
- Allied Gold estimates pre-production development costs for the project at approximately US$500 million.
- The current mine plan is built around 2.7 million ounces of Proven and Probable Mineral Reserves, targeting average production of about 290,000 ounces annually during the first four years.
- Annual production of 290,000 ounces is equivalent to roughly nine metric tonnes of gold.
- Allied Gold holds a 93% ownership interest in the Kurmuk project.
- The company controls a prospective land package of roughly 1,450 square kilometres around the mine for ongoing exploration.
Related
Ethiopian Airlines Unveils 2027 In-Flight Menu Amid Safety Scrutiny
BirrMetrics · yesterday
Quality Standards Developed for Seven Indigenous Food and Beverage Products, Including Injera and Tej
The Reporter (Amharic) · 3 days ago
EU-Backed Fellowship to Support Ethiopian Media Resilience
BirrMetrics · 3 days ago
Nib International Bank Launches Voice-Based Payment Confirmation System
Sheger FM · 3 days ago