Infrastructure

Bole Arabsa-ICT Park Road Project Resumes Under Internal Management

TIKVAH Ethiopia · 4 hours ago · Read the Full Story on TIKVAH Ethiopia
Bole Arabsa-ICT Park Road Project Resumes Under Internal Management
AI SUMMARY

The Addis Ababa City Roads Authority has taken over the Bole Arabsa-ICT Park road project using its own resources after terminating the contract with Alemayehu Ketema due to slow progress.

  • The contract for the Bole Arabsa-ICT Park road project was terminated due to slow progress by the former contractor, Alemayehu Ketema.
  • The Addis Ababa City Roads Authority is currently completing the remaining construction work using its own internal resources.
  • Three bridges included in the project scope will be constructed by a different contractor.
  • The road project covers a total length of 6 kilometers and a width of 60 meters, including pedestrian walkways and green spaces.
  • Sub-base work is currently being carried out extensively on the project.
  • Upon completion, the road will serve as a shortcut from Bole International Airport through Goro to Bole Arabsa and significantly alleviate traffic congestion.